Authored by the expert who managed and guided the team behind the Vietnam Property Pack

Everything you need to know before buying real estate is included in our Vietnam Property Pack
Understanding Vietnam's 1/2000 and 1/500 planning scales is crucial for any property buyer looking to invest safely in the Vietnamese real estate market.
The difference between these two planning scales determines whether you can legally build, obtain financing, and protect your investment. While a 1/2000 plan provides basic zoning approval, only a fully approved 1/500 plan allows construction permits and bank mortgages, making it essential for serious buyers to know which stage a project has reached.
If you want to go deeper, you can check our pack of documents related to the real estate market in Vietnam, based on reliable facts and data, not opinions or rumors.
Vietnam's 1/2000 plans provide general zoning approval but don't allow construction, while 1/500 plans offer detailed specifications required for building permits and bank financing.
Projects typically take 8-12 months to progress from 1/2000 to approved 1/500 status, with property values increasing 10-30% once the detailed planning is approved.
Planning Scale | 1/2000 Plan | 1/500 Plan |
---|---|---|
Legal Authority | District/City People's Committee | District/City People's Committee (approval) |
Level of Detail | General zoning and infrastructure | Exact plot boundaries and specifications |
Construction Permission | Not allowed | Construction permits available |
Bank Financing | Generally not approved | Mortgage financing available |
Development Stage | Initial planning phase | Ready for construction |
Investment Risk | High risk of delays | Lower risk, legally protected |
Typical Timeline | First approval stage | 8-12 months after 1/2000 |

What exactly does a 1/2000 land use plan mean in Vietnam, and how is it legally different from a 1/500 plan?
A 1/2000 land use plan in Vietnam serves as a general zoning blueprint that outlines broad development directions but cannot be used for actual construction.
The 1/2000 plan establishes basic land use zones, infrastructure networks including roads and utilities, and sets development coefficients for a designated area. However, it does not define exact plot boundaries, building specifications, or architectural details that are necessary for construction permits.
In contrast, a 1/500 plan translates the broad 1/2000 zoning into precise, legally binding specifications. This detailed plan includes exact plot dimensions, building lines, setback requirements, utility connections, and architectural guidelines that enable legal construction activities.
The key legal difference is that only an approved 1/500 plan provides the legal foundation for obtaining construction permits, while a 1/2000 plan serves purely as a preliminary zoning document that cannot authorize any building activities.
It's something we develop in our Vietnam property pack.
Which authority issues the 1/2000 plan and which authority approves the 1/500 plan?
Both the 1/2000 and 1/500 plans fall under the jurisdiction of local government authorities, typically at the district or city level.
The 1/2000 plan is usually issued by district-level People's Committees or higher authorities, and in some cases, investors can prepare these plans when no existing locality plan is available. The approval process involves urban planning departments within the local government structure.
For the 1/500 plan, the project investor or developer prepares the detailed planning documents, but the formal approval must come from the local construction authorities, commonly the district or city People's Committee. This approval process involves more rigorous review as it directly impacts construction permits and legal development rights.
The distinction is important because while investors can sometimes initiate 1/2000 plans, they cannot self-approve 1/500 plans, which require official government approval before any construction activities can commence legally.
How precise is the 1/2000 plan in terms of plot size, road layout, and utilities compared to the 1/500 plan?
The precision difference between 1/2000 and 1/500 plans is substantial and directly impacts what can be built and developed.
Planning Element | 1/2000 Plan Precision | 1/500 Plan Precision |
---|---|---|
Plot Boundaries | General zones and areas | Exact measurements and coordinates |
Road Layout | Basic road networks and connections | Precise widths, materials, and specifications |
Utility Infrastructure | General utility corridors | Exact utility locations and connections |
Building Requirements | General land use coefficients | Specific height limits and setbacks |
Environmental Features | General green spaces | Detailed landscaping and drainage |
Access Points | Basic access directions | Specific entrance and exit locations |
Construction Guidelines | General building orientations | Detailed architectural requirements |
At what stage of a project is the 1/2000 plan required, and when does the 1/500 plan come into play?
The 1/2000 plan is required immediately after receiving principle investment approval but before any detailed project design can begin.
This plan acts as the essential precondition for further project development and serves as the foundation for all subsequent planning activities. Developers cannot proceed with detailed design, marketing, or sales activities without an approved 1/2000 plan in place.
The 1/500 plan comes into play after the 1/2000 plan has been completed and approved. This detailed plan represents the final major planning hurdle before construction permits can be obtained and actual building activities can commence.
The sequence is critical: developers must complete the 1/2000 planning stage before they can even begin preparing the more detailed 1/500 plan documents. This staged approach ensures that projects progress through proper legal and technical review processes before reaching the construction phase.
Don't lose money on your property in Vietnam
100% of people who have lost money there have spent less than 1 hour researching the market. We have reviewed everything there is to know. Grab our guide now.

How long does it typically take for a developer in Vietnam to move from a 1/2000 plan to an approved 1/500 plan?
The progression from 1/2000 to approved 1/500 plan typically takes 8-12 months for most residential and commercial projects in Vietnam.
The timeline breaks down into two main phases: completing the 1/2000 plan takes approximately 4-6 months, while preparing and obtaining approval for the 1/500 plan requires another 4-6 months of regulatory review and technical refinement.
However, complex projects or developments in areas with challenging regulatory environments can extend this timeline significantly. Large-scale developments, projects requiring environmental impact assessments, or those facing local opposition can take 18-24 months or longer to complete both planning stages.
Factors that can delay the process include incomplete documentation, changes in local regulations, infrastructure requirements that exceed initial estimates, and the need for additional government approvals. As of September 2025, streamlined procedures have reduced some delays, but buyers should still expect the full planning cycle to take at least one year.
Which of the two plans actually allows a buyer to get construction permits and start building legally?
Only a fully approved 1/500 plan allows buyers or developers to obtain construction permits and start legal building activities.
The 1/2000 plan, while necessary for the planning process, provides no legal authority for construction permits or building activities. Projects that have only completed the 1/2000 stage cannot legally proceed with any construction, alterations, or development activities.
Vietnamese construction law explicitly requires an approved 1/500 detailed plan before any construction permits can be issued. This requirement exists because the 1/500 plan contains the precise technical specifications, safety requirements, and infrastructure details that construction authorities need to evaluate permit applications.
Buyers who attempt to build based solely on a 1/2000 plan face significant legal risks, including construction stop orders, fines, and potential demolition of unauthorized structures. The legal framework is clear: construction permits are only available after 1/500 plan approval.
It's something we develop in our Vietnam property pack.
How do banks in Vietnam treat 1/2000 vs 1/500 plans when it comes to granting mortgages or project financing?
Vietnamese banks generally require an approved 1/500 plan before granting mortgages or project financing, treating the 1/2000 plan as insufficient collateral.
Banks view the 1/2000 plan as preliminary zoning approval that carries too much development risk for mortgage lending. Since projects at this stage cannot obtain construction permits or guarantee completion, banks consider them unsuitable for standard residential or commercial lending programs.
Financial institutions require the certainty that comes with 1/500 approval because this detailed plan provides the legal foundation for property development and construction. Banks can more accurately assess project viability, completion timelines, and property values when detailed planning is complete.
For project financing, developers typically need to progress beyond the 1/2000 stage before securing construction loans or development financing from major Vietnamese banks. Some specialized lenders may provide limited pre-development financing for 1/2000 stage projects, but these loans carry higher interest rates and more restrictive terms.
What are the risks for a buyer if they invest in a project that only has a 1/2000 plan approved but not a 1/500?
Investing in projects with only 1/2000 plan approval carries significant financial and legal risks that can result in total investment loss.
The primary risks include:
1. **Project cancellation risk** - Without 1/500 approval, projects can be cancelled due to regulatory changes, zoning conflicts, or developer financial problems2. **Indefinite delays** - Projects may remain stalled at the 1/2000 stage for years due to bureaucratic obstacles or technical complications 3. **No construction possibility** - Buyers cannot build, renovate, or develop their property without 1/500 approval4. **Financing limitations** - Banks will not provide mortgages for properties in 1/2000-only developments5. **Legal disputes** - Unclear development rights can lead to ownership conflicts and legal challenges6. **Investment illiquidity** - Properties cannot be easily sold or transferred without proper development approvals7. **Infrastructure uncertainty** - Utilities, roads, and community facilities may never be completed without detailed planningBuyers who invest at the 1/2000 stage essentially become partners in a speculative development venture rather than purchasing a viable property asset.

We did some research and made this infographic to help you quickly compare rental yields of the major cities in Vietnam versus those in neighboring countries. It provides a clear view of how this country positions itself as a real estate investment destination, which might interest you if you're planning to invest there.
How can a buyer verify if a project in Vietnam has reached the 1/500 stage and see the official documents?
Buyers can verify 1/500 approval status through official government channels and by requesting specific documentation from developers.
The verification process involves checking with the local construction authority, typically the district or municipal People's Committee, where 1/500 approvals are publicly recorded. These approvals are matters of public record and must be accessible for inspection by potential buyers.
Buyers should request the following documentation from developers: official 1/500 approval certificates, detailed planning drawings with government stamps, construction permit eligibility letters, and infrastructure development schedules. Legitimate developers will readily provide these documents as they are required for legal sales activities.
Additionally, buyers can visit the local planning department to review project files and confirm approval status independently. Online government portals in major cities like Ho Chi Minh City and Hanoi also provide searchable databases of approved development projects.
On average, how much project value or land price difference exists between a development at 1/2000 stage and at 1/500 stage?
Properties and land in developments with approved 1/500 plans typically command 10-30% higher prices compared to those at the 1/2000 stage.
This price premium reflects the reduced risk and increased development certainty that comes with detailed planning approval. Projects at the 1/500 stage offer buyers legal protection, financing options, and construction capability that are unavailable at earlier planning stages.
In Vietnam's major cities, the price differential can be even more pronounced during strong market conditions. Ho Chi Minh City and Hanoi developments often see 20-40% price increases once 1/500 approval is secured, particularly in prime locations where development rights are highly valuable.
The price gap also reflects the time value of money and development risk. Buyers who purchase at the 1/2000 stage may wait 1-2 years for 1/500 approval, during which time they cannot build, obtain financing, or fully utilize their property investment.
It's something we develop in our Vietnam property pack.
What practical signs should a buyer look for on-site that indicate whether the project has moved beyond 1/2000 planning?
Several visible indicators at the project site can help buyers assess whether a development has progressed beyond basic 1/2000 planning.
Key on-site signs of advanced planning include:
1. **Precise plot demarcation** - Clear boundary markers showing exact plot dimensions and coordinates2. **Detailed construction fencing** - Professional fencing displaying actual construction permits and project specifications3. **Infrastructure development** - Commenced utility installations, road surfacing, and drainage systems4. **Site offices with permits** - Construction site offices displaying official building permits and approval documents5. **Surveying equipment** - Active surveying work indicating precise measurement and boundary establishment6. **Utility marking** - Clear marking of water, electricity, and sewerage connection points7. **Construction access roads** - Properly constructed access roads meeting municipal specifications8. **Environmental compliance** - Visible environmental protection measures and waste management systemsBuyers should also look for posted signs displaying project approval numbers, construction permit references, and contact information for local construction authorities, which indicate proper regulatory compliance.
If a project is stuck at 1/2000 approval for years, what options does a buyer have to protect their investment?
Buyers facing prolonged delays at the 1/2000 stage have several legal and financial options to protect their investment.
Immediate protective actions include reviewing purchase contracts for delay clauses and refund provisions, as many contracts include specific timelines for planning approvals and construction commencement. Buyers can often request partial or full refunds if developers fail to meet contractual development milestones.
Legal remedies include consulting Vietnamese real estate lawyers to assess breach-of-contract claims, filing complaints with local construction authorities about project delays, and joining with other buyers to petition for regulatory intervention or project cancellation.
Financial protection strategies involve suspending additional payments until 1/500 approval is secured, negotiating revised payment schedules tied to development milestones, and exploring insurance options that may cover investment losses due to development failures.
The most important protective measure is avoiding investment in projects that lack 1/500 approval, as prevention is more effective than remediation when dealing with Vietnamese property development risks.
Conclusion
This article is for informational purposes only and should not be considered financial advice. Readers are advised to consult with a qualified professional before making any investment decisions. We do not assume any liability for actions taken based on the information provided.
Understanding the difference between 1/2000 and 1/500 planning scales is essential for making safe property investments in Vietnam's developing real estate market.
Buyers who invest only in projects with approved 1/500 plans benefit from legal protection, financing options, and construction certainty that make their investments significantly more secure.
Sources
- Song Nam - Difference Between Detailed Planning 1/500 and Planning 1/2000
- Japan Science and Technology Agency - Urban Planning Research
- Song Nam - Master Plan Design Scales
- World Bank - Vietnam Urban Development
- Long Phan PMT - Approval Procedure for 1/500 Detailed Plan
- Vietnam News - Construction Procedures
- VTN Partners - Social Housing Project Challenges
- MBS - Residential Property Report
- World Bank - Vietnam Scaling Up Report
- Indochine Counsel - Vietnam Property Development Guide